Construction Update in Dumbo (Week of Aug 8 2011)

Belgian Blocks on Water Street

Putting the tracks back into the street

The following is this week’s anticipated construction work schedule (7am – 3:30pm work hours), field conditions permitting for this week. Please note that parking may be restricted in work areas.

  • 8/5/11 through 8/12/11 – Washington Street between York/Water Street – Prepare roadway for the reinstalling the Belgian Blocks
  • 8/5/11 through 8/12/11 – Washington Street between Water/Plymouth Street – Continue excavation of roadway for installation of concrete base
  • 8/5/11 through 8/12/11 – Water Street between Washington/Adams Street – Start the reinstallation of the Belgian Blocks and install Belgian Blocks bicycle lane
  • 8/5/11 through 8/12/11 – Water Street and Main Street intersection – Complete installation of Belgian Blocks

For more information, please call Paul Kidder, the Community Construction Liaison at 718-643-2850 or email: waterstreetccl@gmail.com

For prior construction posts, see dumbonyc.com/tag/construction.