The following is this week’s anticipated construction work schedule (7am – 3:30pm work hours), field conditions permitting for this week. Please note that parking may be restricted in work areas.
- 3/4/11 through 3/11/11 – Water Street/Adam Street intersection near the Manhattan Bridge, Continue installation of chambers, valves and manholes
- 3/4/11 through 3/11/11 – Washington Street between Water Street and PLymouth Street, Excavate and prepare sewer trench for Auger piles and final section of sewer pipe
- 3/4/11 through 3/11/11 – Washington Street intersection at Plymouth Street and inside the DEP yard, Continue excavation for the installation of valves, chamber and manholes
- 3/4/11 through 3/11/11 – Front Street/Washington Street intersection between Main Street, Excavation and removal of boulder; installation of the final sewer and water connection at this location
NOTE: The B25 Bus line has been returned to the original route along Water Street.
Looking ahead:
- Water St. from Main St. to Adams St.: Continue the installation of new granite curb, sidewalk and Belgian block roadway.
- Washington St. between York St. and Water St: Continue the installation of new granite curb, sidewalk and Belgian block roadway.
For more information, please call Paul Kidder, the Community Construction Liaison at 718-643-2850 or email: waterstreetccl@gmail.com
Previously:
{Construction Update in Dumbo (Feb 2011)}
{Pile Driving on Washington Street, 17Dec2010}
{Two Way Washington Street, 10Nov2010}
{Washington Street Construction (Oct 19 Update)}
{Washington Street Construction (Sept Update), 22Sept2010}
{Asbestos Abatement Project, 27Aug2010}
{Washington Street Construction Update, 13Aug2010}
{Construction Around Dumbo Through 2011+, 10May2010}
{Notice: Cars Parked on Dock Street, 12Apr2010}
{Water Street Reconstruction Update (Mar/Apr 2010), 10Mar2010}
{Water/Washington St Reconstruction Project Update, 03Dec2009}
{Belgian Block Reconstruction to Begin, 04May2009}
Great photo!
Love the car service that seems to be stuck in the hole in the intersection!
Plus the back hoe looks about to bash open the doors of 55 Washington Street!
Great photo!
Love the car service that seems to be stuck in the hole in the intersection!
Plus the back hoe looks about to bash open the doors of 55 Washington Street!
Pingback: Dumbo NYC, Brooklyn » Archive » Washington Street Sidewalk Repair (DumboNYC.com)
Pingback: Dumbo NYC, Brooklyn » Archive » Washington Street Sidewalk Repair (DumboNYC.com)
what is the investment potential for units in OBBP?? What is the prevailing rent per sq foot?
what is the investment potential for units in OBBP?? What is the prevailing rent per sq foot?