Construction Update in Dumbo (Feb 2011)

Dumbo Snow - 1/27/11

(Photo by Steve Talkowsk)

The following is the anticipated construction work schedule (7am – 3:30pm work hours), field conditions permitting for this week. Please note that parking may be restricted in work areas.

  • 1/4/11 through 2/11/11 – Old Fulton Street B/T Everit Street and Furman Street at Pier # 1, Finish the Roadway restoration and 6” air cock connection
  • 1/4/11 through 2/11/11 – Washington Street B/T Water Street and Front Street, Backfill the entire trench and place Temp. asphalt on the roadway
  • 1/4/11 through 2/11/11 – Washington Street B/T Water Street and Plymouth Street, Backfill over the 15” sewer and excavate for the sewer installation at Plymouth St.
  • 1/4/11 through 2/11/11 – Water Street B/T Washington Street and Adams Street, Continue Excavating and installing 36” Trunk Main and valve chambers

For more information, please refer to the Community Advisory Notice sent to us by The New York City Department of Design and Construction (NYCDDC) (PDF here), which is managing a capital construction project on Water Street from Adams Street to Old Fulton Street and Washington Street from York Street to Plymouth Street.

For More Information Contact: The Community Construction Liaison Paul Kidder 718-643-2850.

Previously:
{Pile Driving on Washington Street, 17Dec2010}
{Two Way Washington Street, 10Nov2010}
{Washington Street Construction (Oct 19 Update)}
{Washington Street Construction (Sept Update), 22Sept2010}
{Asbestos Abatement Project, 27Aug2010}
{Washington Street Construction Update, 13Aug2010}
{Construction Around Dumbo Through 2011+, 10May2010}
{Notice: Cars Parked on Dock Street, 12Apr2010}
{Water Street Reconstruction Update (Mar/Apr 2010), 10Mar2010}
{Water/Washington St Reconstruction Project Update, 03Dec2009}
{Belgian Block Reconstruction to Begin, 04May2009}

16 Comment